The 6th floor is completed. Our team works very hard to make this wonderful New Year gift for all of you.
The structure of roof garden is finished too. Soon, we will see 7th and roof top floor.
Huge construction progress in February, now all floors are already completed. Generator, transformer and MDF are on site. Water piping system, electricity system, air condition system, main stairs, lobby, juristic person office, etc
are nearly completed too. Lastly, internal wall of 2nd to 4th floor are done.
The main swimming pool on roof was already filled by cement. Kid pool and deck area will be begun soon.
Plastering the internal wall and installing balcony rails are completed in certain floors.
The preparation of septic tanks (sewage treatment system) is on process.
By making respect to the Guardian Spirit of the land, we, The Unity Patong team believes that we will have given ourselves, our business partners and our clients some good luck in business and life.
Before officially starting construction in May 2012, we already did soil test, bearing load test, cleared some parts of land, plot gridline to locate the foundation area and drilling some rocks.
The construction is officially started! Our two backhoe loaders work 8 hours per day to complete excavating work within one month.
We already removed the old show unit and built temporary worker camp. We also installed the temporary protection to enhance the security for building I and to scope the construction area.
After one month excavating work, we require to adjust construction plan due to many huge solid granite rocks on the ground.
Original plan was to start the whole foundation at the same time however our professional consultant team suggests to do by zoning. Even though there are some delays in foundation, tentative completion day will remain the same.
Foundation and underground water tanks are 100% completed however
with everyday raining, we still could not do soil compacting in order to precede the 1st floor. We hope to get sunshine for 4-5 days so that we could finish the 1st floor soon.